When Dorchester County summarized public comments on its Parsons Road plan this year, one intersection came up by name. Commenters, the county wrote, "suggested a traffic signal at the Parsons Road/Mt. McKinley Drive intersection to improve safety for residents entering and exiting the Summit neighborhood."
That sentence matters to anyone comparing The Summit with other Summerville neighborhoods this winter. The road outside the neighborhood's entrance is already designed and paid for, and it has a construction window. A buyer who closes in 2027 will drive today's Parsons Road for about two years. After that comes roughly three and a half years of construction, and then a different road. How long you plan to own the house determines which of those three you will actually live with, and which one you'll be showing to your own buyer someday.
The road the county has drawn
The Parsons Road project covers about 1.37 miles of Parsons Road between Central Avenue and W. Richardson Avenue. Today it has two lanes. The preferred design the county showed at its April 23, 2026 public meeting has three: one 12-foot travel lane in each direction and a 15-foot two-way left-turn lane down the middle. The design also adds a 10-foot shared-use path on the west side, a sidewalk of 5 to 8 feet on the east side, curb and gutter, and enclosed drainage.
The center lane is a painted turn lane, not a landscaped island. Some commenters asked for raised, planted medians instead. The county says medians are not proposed now but "will be re-evaluated as the design is further refined."
The speed limit and the curves change too. Parsons is posted at 45 mph today, drops to 35 mph near W. Richardson, and has two sharp curves with 35 mph advisory signs. Under the plan, the posted limit becomes 40 mph, the 35 mph zone near W. Richardson stays, and both curves are realigned so far that the county says curve warning signs will no longer be needed.
Why Mt. McKinley Drive gets a straighter curve instead of a light
According to the county, community members "repeatedly identified" Parsons and Mt. McKinley as a priority spot for a signal, citing a history of collisions on the curve there. The county evaluated a signal there and decided against it, saying turning volumes were too low. Its answer is the realignment: "The realignment of the curve approaching the intersection will provide more visibility to approaching vehicles."
For a buyer, this is the most useful detail in the whole plan. It describes what the turn out of The Summit will be like after 2032. You'll still pull out without a signal. But you'll be looking down a straighter road at oncoming traffic posted 5 mph slower than today, and a continuous center lane will give left-turners a place to wait. People who live along Parsons supported that turn lane, according to the county's summary. Commenters also worried that drivers will keep speeding after the limit drops, and that the work could affect property and neighborhood entrances. On access, the county says the design aims to keep full access to adjacent properties where possible, and that "access to properties will be preserved" even where access patterns are modified.
The calendar you are buying into
The county's April 2026 materials and the news coverage around them set out these dates:
- Right-of-way acquisition was expected to begin in early 2027. Live 5 reported on April 22, 2026 that the county anticipated starting it "early next year."
- Construction on Parsons Road and Central Avenue is planned to run at the same time, beginning in early 2029 and taking approximately 3.5 years.
- Counting forward from the county's own figures, that puts completion around mid-2032. The county has not printed a finish date. Mid-2032 is simply early 2029 plus three and a half years.
Now line that schedule up against the time you expect to own. If you close in spring 2027 and stay five years, you would list in spring 2032. On the county's current schedule, that falls in the final months of construction, and your buyers would tour the house with work zones at the entrance. If you stay seven years, you would sell into the finished road. If you are buying now and expect a military reassignment or another short-term move within three years, you would sell in 2029 or 2030, around the start of construction, and your buyer would be the one making this same calculation.
Because the construction years are on a published schedule, you can plan for them before you buy. The county says it does not expect full daytime closures at the major intersections, including Parsons Road at West Richardson Avenue. Lane closures may happen outside rush hours, and access for property owners and emergency vehicles "will be maintained at all times." If you're already weighing timing on the selling side, our post on when to list in The Summit covers the seasonal side of that question.
How firm the plan is
A road plan only helps your decision if it's likely to get built. This one has its money. The county's April 2026 handout puts the estimated total cost at $19,131,042 for Parsons Road and $75,701,346 for the Central Avenue project, On its project page, the county says both are funded through construction. The funding comes from the Dorchester County Transportation Sales Tax Program. On November 8, 2022, county voters chose to continue the existing one percent sales and use tax that pays for the program's project list, and that list includes Central Avenue and Parsons Road.
The reason behind the project also bears on value. The county projects that average daily traffic on Parsons Road will rise 86 percent by 2050. Without the work, it expects the Parsons Road and Central Avenue intersection, among others, to fail by then. That analysis is built on 2023 traffic data, plus a February 2025 supplemental count at White Gables Drive for the roundabout planned on Central Avenue. Some commenters asked for a fresh study, and the county said a new traffic study is not planned.
So the 2032 road is designed for more traffic than Parsons carries now. For a household in The Summit, the wider road is a response to the traffic that's coming.
The design has drawn steady public attention. The June 2025 round of comments produced 110 responses, which the Post and Courier's Journal Scene covered at the time. The second comment period, April 23 to May 23, 2026, brought in 40 more.
The other end of Parsons is changing, too
Parsons Road ends at W. Richardson Avenue, the road many Summit households take toward downtown. That road is changing hands. At its June 11, 2026 meeting, Summerville Town Council voted to have staff start the process of taking West Richardson Avenue over from SCDOT and to lower its speed limit to 25 mph. Mayor Touchberry noted at the meeting that the takeover "will most likely cost the Town more in maintenance than is in the current budget," according to the council minutes.
Live 5 reported on June 15, 2026 that town staff had begun the process for the stretch of West Richardson from Main Street to Maple Street, the road the station called "the main gateway into Summerville from the west." Together, the two projects show both governments working on the same drive: the county is rebuilding the stretch outside The Summit's entrance, and the town is moving to slow the stretch closer to downtown. If evening walks and short trips into town are part of why you're looking here, our earlier post on The Summit's three walking loops covers what's inside the neighborhood.
Questions to settle before you make an offer
Some details in the design aren't final yet. A few of them could affect a particular house.
Noise walls are one. The county's April 2026 materials list five potential noise-wall locations along the corridor, two of them on Parsons Road. The county calls those findings preliminary and says final wall decisions will come once design is complete.
The plan sheets are another. The county says the preferred-alternative drawings from April 2026 show the proposed improvements and future right-of-way lines, and that they are "subject to change" as design moves forward. The project team takes questions at [email protected], which is also the place to ask how the drawings affect a specific lot near Mt. McKinley Drive.
The milestones are the third. The county posts updates on its Parsons Road and Central Avenue project pages and through its Transportation Sales Tax email list. If right-of-way work starts on schedule in 2027, that will be the first sign the 2029 construction start is holding. If it slips, the rest of the timeline above slips with it.
If you're comparing The Summit with other Summerville neighborhoods and want to see how the Parsons Road timeline lines up with your own plans, whether that's a PCS window, a five-year move-up, or a longer stay, give The Angela Miller Team a call and we'll go through the county's dates with you. To get started, request a free home valuation and neighborhood guide.